CASE STUDY

New Kapalama Container Terminal

Tie-Bar Protection

Project Data

LocationHonolulu, HI
Completion2021 - 2024
Project TypeTie-Bar Protection
Contractor AppliedKiewit
Products UsedDensyl Tape & Viscotaq PVC Outerwrap

   The New Kapalama Container Terminal Phase 2 Project was constructed from 2021 to 2024 and features an 84-acre container yard and 1,863 linear feet of additional berthing capacity. Over 115,000 cubic yards of concrete was poured and over 80,000 feet of 3″ and 3-1/2″ tie-bars were installed to secure the foundation. With the highly corrosive marine environment that the harbor is faced with, the Hawaii DOT Engineers selected Densyl Tape and Viscotaq PVC Outerwrap to protect the tie-bars from corrosion.

   Prior to installation, the 45′ and 30′ pieces of tie-bars were wrapped with 4″ wide Densyl Tape spirally with a 55% overlap. Next, 4″ wide Viscotaq PVC Outerwrap was applied spirally with a 55% overlap to provide additional mechanical protection during handling and installation. After the protected tie-bars were installed, a final layer of protection was utilized by sliding PVC pipes over the surface. 

   By utilizing the Denso Petrolatum Tape System to protect the tie-bars at the Kapalama Container Terminal, The Hawaii DOT knows that the structures foundation will be sound well past the design life.